Vogel Bros. served as the General Contractor for a wastewater treatment facility expansion and disc filter relocation project designed to increase treatment capacity and improve operational efficiency.
The project expanded the facility’s treatment capacity to 0.75 million gallons per day (MGD), supporting current demand and accommodating future growth. Work included process upgrades, structural and mechanical improvements, and integration of new equipment to enhance overall plant performance.
A key component of the project involved the relocation of existing disc filters to optimize process flow and system efficiency. This effort required detailed coordination of mechanical, electrical, and controls systems to ensure seamless integration within the active treatment environment while minimizing operational disruptions.
Through careful planning, phased construction, and close collaboration with plant operations staff, Vogel Bros. successfully delivered critical infrastructure improvements that strengthened system reliability and long-term treatment capabilities.